Done!!! All 6 courts are now complete, Enjoy!!!




Mon - Complete 1st color today

Tues -  Rain day

Wed – 2nd coat –color

Thurs – Lines

Fri – Nets, final


Extend gravel borders, construction fence, this week depending on crew availability.  Girls tryouts are scheduled, let Mr. Labriola know if for any reason courts are not available and let me know immediately if Oval needs to do something to allow for use.


8/10- Second Bay of 3 courts! 2nd coat of violet complete, with 2nd coat of green and lines to follow Wednesday-Friday.

7/31- First Bay of 3 courts completed! (10 and under lines to follow next week)


7/31- Walkways and Sitework completed!)


Week of 7/15...

Week of 7/1...




Week of June 8-12:

Fence posts: courts 4,5,6

Retaining walls

Sub-base stone: 4, 5, 6 in place, rolled in 6” lifts

Recycled item in place, begin screeding to plus or minus ½”

Majority of topsoil removed from site


Projected for Week of June 15-19:

Recycled to grade

Net post footings courts 4,5,6

Pave courts 4,5,6 (weather dependent) or proceed with sub-base for courts 1, 2, 3




Tentative Construction initial schedule for 
John Jay Tennis Courts








5/14 (or 5/15 if Necessary)

Install perimeter steel, fabric fence, sanitary facility delivered



Deliver track loader, excavator, traction pad; begin excavation for water retention soil inspection



proceed with excavation, soil stockpile

We should the the 1st layer of courts paved as early as next week, very exciting!!

May 18th Groundbreaking!



Ground-Breaking ceremony Monday, May 18th at JJHS!


2015- All Approvals have been satisfied! (State Education Department, State Deparment of Environmental Protection, Department of Environmental Conservation, KLSD Board of Education)

Help make the JJHS Tennis Complex a reality by donating at: